Chris Mulder conducted a condition survey of Manitoba Hydro’s self‐propelled, trailerable work barge in order to assess the extent of work required to attain a further 25 years of service life from the vessel. Following the condition survey, CMDL produced a refit plan and detailed refit design package for the vessel and obtained plan approval from Transport Canada. Chris Mulder provided procurement support throughout the tendering process and is currently providing construction supervision services, including on‐site inspections, as the project advances.
Client: Manitoba Hydro
Dates: 2011 – Current